| Funder | Export-Import Bank of China (China Eximbank) |
|---|---|
| Recipient Organization | Zambia Ministry of Finance |
| Country | Zambia |
| Start Date | Oct 13, 2014 |
| End Date | Jul 06, 2032 |
| Duration | 6,476 days |
| Number of Grantees | 1 |
| Roles | Recipient |
| Data Source | AidData Chinese Aid |
| Grant ID | 40801 |
China Eximbank provides $45 million loan for 330kV Kariba North Bank-Kafue West Transmission Line Project On March 4, 2014, the Chinese Ambassador and the Zambian Minister of Finance signed a $41 million loan framework agreement for the 33kV Kariba North Bank-Kafue West Transmission Line Project.
Then, on October 13, 2014, China Eximbank and the Zambia Ministry of Finance signed a $45 million loan agreement to support this project.
According to ZESCO's Report and Financial Statements, as of December, 31 2017, 100% of the loan funds had been drawn down.
The proceeds from the loan were used to fund the construction of a 120 km power transmission line between the China Eximbank-financed Kariba North Bank Hydropower Plant (see Record ID#354) and Kafue West substation. Sinohydro was the contractor responsible for implementation. The project officially commenced on March 18, 2013 and construction ended on or around October 25, 2014.
On December 15, 2014, power was successfully evacuated from the Kariba North Bank Hydropower Plant to the newly constructed transmission lines and then onward to the Lusaka power grid.
1. The Chinese project title is 卡里巴-卡富韦输电线路 330kV 129KM or 赞比亚KK330输电线路工程 or 赞比亚卡里巴北至凯富埃西330kV输电线路项目.