Completed Development AidData Chinese Aid

Chinese Government provides grant worth 21.5 million Kina for Usino Junction-Yamagi Road Project (Linked to Record ID#64520 and Record ID#64653)

$21.5M USD

Funder China Ministry of Commerce
Recipient Organization Government of Papua New Guinea
Country Papua New Guinea
Start Date Jan 19, 2011
End Date Nov 23, 2029
Duration 6,883 days
Number of Grantees 1
Roles Recipient
Data Source AidData Chinese Aid
Grant ID 39370
Grant Description

On January 19, 2011, the Chinese Government provided a grant worth 21.5 million Kina to the Government of Papua New Guinea for the Usino Junction-Yamagi Road Project.

This project involved the construction of a 16.026 km, 7.5 meter wide access road with six bridges and 24 culverts and it was designed to increase access to the site of the China Eximbank-financed Ramu Nickel-Cobalt Project (captured via Record ID#64520 and Record ID#64653) as well as a new port at Basamuk Bay.

The road begins at Usino Junction (also known as Usino Junction-Yamagi Road) and ends at the Yamagi broken bridge (in Usino-Bundi electorate and Madang Province).

The road then connects to the an access road developed by the Chinese contractor (MCC) responsible for the Ramu Nickel-Cobalt Project.

The purpose of the Usino Junction-Yamagi Road Project was to transport minerals (mainly nickel and cobalt) from the Ramu (also known as Kurumbukari or KBK) mine site to the port at Basamuk Bay.

The project was designed by China Communications Highway Planning and Design Institute Co., Ltd., implemented by China Metallurgical Science and Industry Corporation, and supervised by Guangzhou Wanan Construction Supervision Co., Ltd. The project was originally expected to commence implementation in April 2011 and finish in April 2013.

However, it ultimately began construction on November 10, 2011 and reached completion ahead of schedule on December 12, 2012. 100 PNG nationals were reportedly employed during the implementation of this project.

📋 Staff Comments

For locational coordinates, the Lowy Institute lists the latitude of the project as -6.5861674, and the longitude as 145.6689636.

📚 Sources & References
  • K21.5m for Usino Bundi road
  • Chinese build road
  • 巴布亚新几内亚尤亚公路项目施工纪实
  • 尤亚公路项目顺利通过中期验收
  • 驻巴布亚新几内亚大使仇伯华出席尤亚公路项目开工仪式
  • 中巴新签署援巴新尤亚公路施工合同
  • 驻巴布亚新几内亚大使仇伯华出席尤亚公路项目开工仪式
  • I will start the groundbreaking ceremony for the Baxin You-Asia Highway Project
  • Assistance to the Papua New Guinea Yu-Asia Highway Project
  • 驻巴布亚新几内亚大使仇伯华在尤亚公路开工仪式上的讲话
  • The Samoan Experience: Aid Relations with China
  • Lowy Institute Pacific Aid Map Database.xlsm
  • Cobalt 27 FilesNI 43-101 Technical Report onthe ProducingRamuNickel-Cobalt Project
  • AGENCY SUMMARY OF ALL PROJECTSEXPENDITURE PROJECTIONS AND FINANCING REQUIREMENTS
  • AGENCY SUMMARY OF ALL PROJECTSEXPENDITURE PROJECTIONS AND FINANCING REQUIREMENTS 264
  • Road for Usino
  • Chinese build bridges to suit PNG condition
  • Remarks by H. E. Chinese Ambassador Mr.Qiu Bohua Loan applications and disbursements are still being received and processed as the projects continue to evolve. Ongoing monitoring and evaluation are in place to ensure project continuity.
All Grantees

Government of Papua New Guinea

Advertisement
Discover thousands of grant opportunities
Advertisement
Browse Grants on GrantFunds
Interested in applying for this grant?

Complete our application form to express your interest and we'll guide you through the process.

Apply for This Grant