| Funder | Export-Import Bank of China (China Eximbank) |
|---|---|
| Recipient Organization | Government of Togo |
| Country | Togo |
| Start Date | Feb 14, 2014 |
| End Date | Jan 27, 2028 |
| Duration | 5,095 days |
| Number of Grantees | 1 |
| Roles | Recipient |
| Data Source | AidData Chinese Aid |
| Grant ID | 36406 |
China Eximbank provides RMB 210 million government concessional loan for the Lomé and 10 Interior Towns Electricity Distribution Network Project On December 27, 2013, as part of a series of agreements signed (for these other agreements, see linked Record ID#72803), Chinese Ambassador to Togo, Liu Yuxi, and Togolese Minister of Economy and Finance, Adji Othèth Ayassor, signed am RMB 210 million (or CFA 15 billion franc) preferential loan framework agreement for the Lomé and 10 Interior Towns Electricity Distribution Network Project.
Then, on February 14, 2014, the Export-Import Bank of China and the Ministry of Economy and Finance of the Republic of Togo finalized the RMB 210 million government concessional loan (GCL) agreement for the project.
The proceeds of the loan were used to finance a commercial contract with TBEA that was signed on April 26, 2012. China Eximbank disbursed $15,488,980 in support of the project in 2015.
The project involved the strengthening of an electricity distribution network in the capital city of Lomé and in 10 towns in the interior of Togo.
TBEA Co., Ltd. was the contractor responsible for implementation; its affiliate TBEA Nanjing Intelligent Electric Co., Ltd. was also involved in implementation. Togo's Ministry of Mines and Energy was the project's beneficiary ministry.
The project has entered implementation because some of the loan proceeds have been disbursed, but its precise implementation start and end dates are unknown.
Government of Togo