Loading…
Loading grant details…
| Funder | Export-Import Bank of China (China Eximbank) |
|---|---|
| Recipient Organization | Government of Uganda |
| Country | Uganda |
| Start Date | Feb 20, 2015 |
| End Date | Jul 18, 2033 |
| Duration | 6,723 days |
| Number of Grantees | 1 |
| Roles | Recipient |
| Data Source | AidData Chinese Aid |
| Grant ID | 36211 |
China Eximbank provides $645.82 million buyer’s credit loan for 600 MW Karuma Hydropower Dam and Associated Transmission Lines and Sub-stations Project On December 18, 2014 and February 20, 2015, China Eximbank and the Government of Uganda signed two loan agreements worth a total of $1,435,158,682 for the 600 MW Karuma Hydropower Dam and Associated Transmission lines and Sub-stations Project.
Then, on February 27, 2015, the Parliament of Uganda ratified these two loan agreements.
Under the terms of the BCL, the Government to Uganda is responsible for on-lending the full amount of the loan to Uganda Electricity Generation Company Limited (UEGCL) and the Uganda Electricity Transmission Company Limited (UETCL).
The proceeds from the BCL and the PBC were to be used by the borrower to finance 85% of the total cost of a $1,688,421,979.39 commercial contract between the Government of Uganda’s Ministry of Energy and Mineral Development and Sinohydro Corporation Limited, which was signed on August 16, 2013 and amended on May 6, 2014 and May 15, 2014 (via Addendum No. 1 and Addendum No. 2).
The borrower was to use the BCL proceeds to finance 38.25% of the commercial contract cost and the PBC proceeds to finance 46.75% of the commercial contract cost.
The Government of Uganda provided a sovereign guarantee for both China Eximbank loans, and the Government of Uganda was obligated under the terms of these loans to open escrow accounts with Stanbic Bank and deposit funds in the accounts over the terms of the loans to facilitate repayment and provide security in the event of default.
As of June 30, 2019, the cash balance of one of these escrow (repayment reserve) accounts was UGX 87,154,247,132 ($26,146,274.13).
UMEME Ltd. became the major privately owned electricity distributor in Uganda in 2005 after winning a 20-year concession to operate UEDCL's main distribution network.
It was involved as a contractual signatory to the Karuma PPA in order to safeguard the repayment mechanism and avoid potential risks of revenues being misallocated.
Loan repayments to China Eximbank were to be made through electricity payments under a power purchase agreement (PPA) with UETCL and UMEME Ltd.
According to the terms of the loan agreements and the PPA, UEGCL was to supply UETCL all available power capacity on “take or pay” basis, which means that UETCL was responsible for paying for all available electricity generated by the dam, and not only what was needed.
However, in 2019, Uganda’s Auditor General discovered that the generation and sales licenses were in contradiction of the PPA and loan agreements because they stated that “the tariff methodology [will] be based on the energy service cost implying that the energy dispatch to UETCL will be influenced by market demand.” According to the Government of Uganda’s Aid Management Platform (AMP), the PBC achieved a 85.4% disbursement rate, with China Eximbank making 24 loan disbursements (worth $674,527,385.55) between 2015 and 2020: a $101,179,038 disbursement on December 24, 2015, a $16,324,648 disbursement on December 25, 2015, a $16,009,159 disbursement on December 28, 2015, a $23,583,642.35 disbursement on April 27, 2016, a $11,850,199 disbursement on July 29, 2016, a $37,208,639 disbursement on September 13, 2016, a $18,949,811 disbursement on December 15, 2016, a $8,637,526 disbursement on April 21, 2017, a $6,927,809 disbursement on June 27, 2016, a $43,705,347.25 disbursement on September 6, 2017, a $28,149,577.68 disbursement on October 18, 2017, a $12,649,419.75 disbursement on November 14, 2017, a $39,929,383.45 disbursement on December 26, 2017, a $48,155,261.48 disbursement on April 13, 2018, a $13,785,395.25 disbursement on May 31, 2018, a $65,799,750.54 disbursement on October 19, 2018, a $7,308,794.90 disbursement on December 25, 2018, a $41,827,450.63 disbursement on February 28, 2019, a $36,212,516.45 disbursement on April 29, 2019, a $13,979,022.20 disbursement on June 20, 2019, a $52,698,924.89 disbursement on November 13, 2019, a $10,010,402.52 disbursement on December 19, 2019, a $14,101,813.11 disbursement on March 20, 2020, and a $5,543,854.10 disbursement on August 18, 2020.
According to the Uganda Ministry of Finance, Planning, and Economic Development's Report on Public Debt, Grants, Guarantees and Other Financial Liabilities for Financial Year 2021/2022, as of December 31, 2021, total loan disbursements amounted to $674,527,385.55 and the loan’s amount outstanding (including arrears) was $674,527,385.55.
According to the Government of Uganda’s Aid Management Platform (AMP), the BCL achieved a 97% disbursement rate, with China Eximbank making 31 loan disbursements (worth $625,602,535.38) between 2015 and 2021: a $31,356,497 disbursement on December 25, 2015, a $30,767,223 disbursement on January 29, 2016, a $58,068,539 disbursement on March 7, 2016, a $8,341,230.65 disbursement on May 26, 2016, a $9,695,618 disbursement on July 29, 2016, a $30,443,431 disbursement on September 13, 2016, a $15,504,390 disbursement on December 15, 2016, a $7,067,066 disbursement on April 21, 2017, a $5,668,207 disbursement on June 29, 2017, a $22,395,381 disbursement on September 1, 2017, a $13,363,539.75 disbursement on September 8, 2017, a $23,031,472.65 disbursement on October 17, 2017, a $10,349,525.25 disbursement on November 15, 2017, a $32,669,495.55 disbursement on December 19, 2017, a $39,399,759.39 disbursement on April 20, 2018, a $11,278,959.75 disbursement on May 29, 2018, a $53,836,159.53 disbursement on October 18, 2018, a $5,979,923.10 disbursement on December 24, 2018, a $34,222,459.61 disbursement on March 1, 2019, a $29,628,422.56 disbursement on April 29, 2019, a $11,437,381.80 disbursement on June 19, 2019, a $43,117,302.18 disbursement on November 12, 2019, a $8,190,329.33 disbursement on December 20, 2019, a $11,537,847.09 disbursement on March 19, 2010, a $8,362,437.84 disbursement on August 19, 2020, a $16,193,030.50 disbursement on November 5, 2020, a $9,772,888.57 disbursement on August 26, 2021, a $8,920,595.93 on March 17, 2022, a $10,602,602.45 disbursement on May 9, 2022, a $14,822,335.90 disbursement on June 17, 2022, and a $9,578,484 disbursement on August 18, 2022.
According to the Uganda Ministry of Finance, Planning, and Economic Development's Report on Public Debt, Grants, Guarantees and Other Financial Liabilities for Financial Year 2021/2022, as of December 31, 2021, total disbursements under the BCL amounted to $581,678,517 and the loan’s amount outstanding (including arrears) was $517,096,376.38.
On July 28, 2021, the Government of Uganda and China Eximbank signed a supplementary agreement to the BCL agreement [ID#14030205015210069A], which extended the loan's availability (disbursement) period to allow for $73,915,778.59 of undisbursed funds to be utilized by the borrower (after the original availability period expired on December 24, 2020).
The supplementary agreement also specified that, if the loan fully disbursed, the borrower would be responsible for making twenty, semi-annual repayments (worth $32,291,070.36 each) between January 21, 2021 and July 21, 2030.
The 600 MW Karuma Hydropower Dam and Associated Transmission lines and Sub-stations Project., which is also known as the Karuma Hydropower Plant and Interconnection Project, will involve the installation of 6 turbines (10 million kilowatts each), which will create a total capacity of 600 MW, making it Uganda's largest power plant.
After the first two turbines start generating electricity, the remaining four turbines will be turned on once per month. The project includes dams, water diversion pipes, underground power plants, and transmission lines.
The purpose of the Interconnection Project is to evacuate power produced from Karuma Hydropower Plant in Northern Uganda to load centers, which include Lira and Olwiyo in Northern Uganda, and Kawanda in Central Uganda.
It will involve construction of a 248km, 400kV, Double Circuit Karuma-Kawanda transmission line; a 78km, 132kV, Double Circuit Karuma-Lira Transmission Line; a 55km, 400kV, Double Circuit Karuma-Olwiyo transmission Line (which will be initially operated at 132kV); a new 400/132kV sub-station interconnecting with Karuma HPP and 400kV line bays; a new 400kV/220kV substation with two new incoming 400kV line bays to interface with the existing Kawanda 220/132kV substation; two new incoming 132kV line bays to interface with the existing Lira 132/33kV substation; and a new 132/33kV Olwiyo substation.
The EPC contractor responsible for implementation of this project was Sinohydro Corporation Limited. The construction of the dam and power station officially started on August 12, 2013. As of March 2016, about 30% of the work had been completed.
In October 2016, it was estimated that about 1,000 Chinese nationals and about 5,000 Ugandans were working at the power station.
As of June 2018, 56 months from the beginning of construction, an estimated 76% of the physical work had been completed. Of the 6,000 workers, 5,300 were Ugandan.
As of September 2019, an estimated 95% of construction activities had been completed, which included 100% completion of the Karuma–Lira High Voltage Line, 100% of the Karuma–Kawanda High Voltage Power Line and 98% of the Karuma–Olwiyo High Voltage Line.
As of December 2020, the Karuma Hydropower dam had reached a 98.7% physical progress rate, the Karuma-Kawanda transmission line had reached a 99.5% physical progress rate, the Karuma-Lira transmission line had reached a 86.4% physical progress rate, the Karuma-Olwiyo transmission line had reached a 95.5% physical progress rate, and the Karuma, Kawanda, Olwiyo, and Lira substations have reached 99.9%, 99.9%, 93% and 99% physical progress rates, respectively.
The COVID-19 pandemic was considered a force major event in that it constrained manufacturing and prevented the shipping of equipment and the travel of experts to facilitate the installation and commissioning of equipment.
Other project implementation challenges have included a dispute between the EPC contractor and a sub-contractor, which halted the finalization of the stringing and energizing of a 2.504 km transmission line; UMEME distribution lines without required minimum clearances at Walusi, and Wabigalo; the vandalism of tower materials; accusations of public waste and corruption; the death of a worker due to allegedly unsafe work practices; and accusations that one worker was engaged in ivory smuggling activities.
The cost of the project also reportedly ballooned from $1.68 billion at least $2.2 billion.
Moreover, the project has raised environmental concerns due to construction occurring within nationally protected areas and potential critical habitats of Uganda.
The last of the six power generation units (turbines) was successfully connected to the national grid on February 6, 2024. The power plant was officially commissioned on September 26, 2024.
Government of Uganda
Complete our application form to express your interest and we'll guide you through the process.
Apply for This Grant