CAMC provides $34.9 million supplier credit for Banaoang Pump Irrigation Project In October 2001, China National Construction & Agricultural Machinery Import & Export Corporation (CAMC) and the Department of Finance of the Government of the Philippines signed a $34,980,616 supplier credit agreement for the Banaoang Pump Irrigation Project (BPIP).
📋 Loan / Grant Terms
💰 Loan Amountfor local farm project and hybrid rice growth (captured via Record ID#34701) and all subsidiary loans issued under this line of credit carried the following terms: a 3% interest rate
📅 Maturity8 years
⏳ Grace Period2 years
💹 Interest Rate3%
This project involved the construction of a pumping station, irrigation channels, a bridge, a tunnel, and power supply and electrical transmission lines — as well as the improvement of farm-to-market roads and drainage infrastructure — in the barangay of Banaoang I within Ilocos Sur district.
It sought to tap water from Abra River that flows from the mountains in the north going west to the West Philippine Sea (South China Sea), and its tributary that flows south was to be the main source of irrigation water.
A pumping station with seven units of electric-powered pumps was to be constructed on the right bank of the river about 150 meters upstream of the Banaoang Bridge.
A 15 km, 67 kilovolt transmission line was to be installed from the National Power Corporation sub-station in Bantay to the project site in order to supply the necessary electricity. A 600 meter tunnel was also to be constructed to connect the pump station to the main canal.
The total length of the main canal was to be about 20.60 km and it was expected to distribute water through a network of lateral and sub-lateral canals (measuring 32 km in length).
Additionally, 90 km of main farm ditches, 176 km of supplementary farm ditches, 50 km O&M roads, and 30 km of drainage canals were to be constructed.
The project was judged, at appraisal, to be economically viable with an economic internal rate of return (EIRR) of 20.0% (above the 15% hurdle rate used by the Government of the Philippines).
Upon completion, it was expected that the project would irrigate 6,312 hectares of land and benefit 5,334 farm households in six municipalities (Vigan, Bantay, San Vicente, San Ildefonso, Sto. Domingo, and Magsingal). CAMC was the contractor responsible for implementation. Its work was overseen by the National Irrigation Administration (NIA) of the Government of the Philippines.
The project commenced in March 2003 and it was originally expected to reach completion in 2006. However, the project experienced a number of delays. Chief among these was the unforeseen occurrence of salt water in the lateral irrigation channels.
The discovery of brackish water in the irrigation channels necessitated an extending of the channels four kilometers more inland to tap sweet water, which was not anticipated when the original project design plans were drawn. The project was officially inaugurated on July 25, 2011.
However, due to unexpected salt water intrusions and associated the cost increases, additional project work continued in 2012 and 2013.
📋 Staff Comments
📚 Sources & References
- China provides loan for Philippine irrigation project.
- CHINA TO PROVIDE USD 35 MLN IN LOAN TO FUND IRRIGATION PROJECT IN NORTHERN PHILIPPINES.
- China Provides Loan for Philippine Irrigation Project.
- Philippines-China relations, 2001–2008: Dovetailing national interests
- Evaluating aid for trade on the ground: Lessons from the Philippines, 2013 Consolidated Audit Report on Official Development Assistance Programs and Projects, 2009 Consolidated audit report on Official Development Assistance projects, 2010 Consolidated audit report on Official Development Assistance projects
- Recently completed projects
- P2.5-B Banaoang Irrigation Project bolsters rice sufficiency efforts in Ilocos
- NIA to fast track Ilocos Sur's P2.4-B irrigation project
- Banaoang Pump Irrigation Project in the Philippines
- RP
- China sign 14 deals boosting bilateral trade.
- 中菲重要双边文件
- 菲律宾巴纳旺农业灌溉工程项目
- 田其祥馆长领事参观巴纳旺灌溉工程
- CY 2008 ODA Portfolio Review Annex 1-B List of Active Programs
- Projects CY 2008
- Philippines-China Infrastructure Cooperation: Lessons and Prospects
- FOREIGN ASSISTED PROJECTS BY DONOR / CREDITOR
- FY 2008-2010
- FOREIGN-ASSISTED PROJECTS BY DEPARTMENT/AGENCY AND SPECIAL PURPOSE FUND
- FY 2008 - 2010
- Consolidated Audit Report on Official Development Assistance (ODA) Projects, 2007 State of the Nation Address
- Bridging the Infrastructure Investment Gap through Foreign Aid: A Briefer on Chinese ODA, 2010 ODA Portfolio Review Annex 3-A List of Active ODA Loans
- CY 2007 ODA Portfolio Review Annex 1-B List of Active Projects Reviewed
- OUTSTANDING EXTERNAL DEBT FROM REGULAR LIABILITIES OF THE NATIONAL GOVERNMENT
- AS OF YEAR-END, 2013-2015, 2008 ODA Portfolio Review
- CHINA’S ECONOMIC DEVELOPMENT ASSISTANCE TO THE PHILIPPINES: A Preliminary Assessment*
- BANAOANG PUMP IRRIGATION PROJECT IN THE PHILIPPINES
- NIB DIRECTOR GENERAL INSPECTS BANAOANG PROJECT
- Banawan Irrigation Project
- Philippines
- DA chief inaugurates P1-billion irrigation facility
- P2.5-B Banaoang Irrigation Project Bolsters Rice
- China Provides Loan for Philippine Irrigation Project
- Banaoang Pump Irrigation Project in the Philippines
- ASN VISITS BANAOANG PUMP IRRIGATION PROJECT
- FOREIGN DEBT SERVICE OF REGULAR LIABILITIES OF THE NATIONAL GOVERNMENT
- BY CREDITOR, 2007-2009
- OUTSTANDING FOREIGN DEBT FROM REGULAR LIABILITIES OF THE NATIONAL GOVERNMENT
- AS OF YEAR END 2007-2009
- FOREIGN DEBT SERVICE FOR REGULAR LIABILITIES OF THE NATIONAL GOVERNMENT
- BY CREDITOR, 2008-2010
- OUTSTANDING FOREIGN DEBT FROM REGULAR LIABILITIES OF THE NATIONAL GOVERNMENT
- AS OF YEAR END 2009-2011
- FOREIGN DEBT SERVICE FOR REGULAR LIABILITIES OF THE NATIONAL GOVERNMENT
- BY CREDITOR, 2010-2012
- OUTSTANDING FOREIGN DEBT FROM REGULAR LIABILITIES OF THE NATIONAL GOVERNMENT
- AS OF YEAR END 2008-2010
- FOREIGN DEBT SERVICE FOR REGULAR LIABILITIES OF THE NATIONAL GOVERNMENT
- BY CREDITOR, 2016-2018
- FOREIGN DEBT SERVICE FOR REGULAR LIABILITIES OF THE NATIONAL GOVERNMENT
- BY CREDITOR, 2009-2011
- OUTSTANDING FOREIGN DEBT FROM REGULAR LIABILITIES OF THE NATIONAL GOVERNMENT
- AS OF YEAR-END, 2016-2018
- OUTSTANDING EXTERNAL DEBT FROM REGULAR LIABILITIES OF THE NATIONAL GOVERNMENT
- AS OF YEAR-END, 2018-2020
- OUTSTANDING FOREIGN DEBT FROM REGULAR LIABILITIES OF THE NATIONAL GOVERNMENT
- AS OF YEAR END, 2010-2012
- EXTERNAL DEBT SERVICE FOR REGULAR LIABILITIES OF THE NATIONAL GOVERNMENT
- BY CREDITOR, 2018-2020
- FOREIGN DEBT SERVICE FOR REGULAR LIABILITIES OF THE NATIONAL GOVERNMENT
- BY CREDITOR, 2017-2019
- REVENUE PROGRAM
- BY SOURCE, 2013 - 2017
- EXTERNAL DEBT SERVICE FOR REGULAR LIABILITIES OF THE NATIONAL GOVERNMENT
- BY CREDITOR, 2020-2022
- NATIONAL GOVERNMENT FINANCING, 2014-2016
- OUTSTANDING FOREIGN DEBT FROM REGULAR LIABILITIES OF THE NATIONAL GOVERNMENT
- AS OF YEAR-END, 2014-2016
- FOREIGN DEBT SERVICE FOR REGULAR LIABILITIES OF THE NATIONAL GOVERNMENT
- BY CREDITOR, 2014-2016
- OUTSTANDING EXTERNAL DEBT FROM REGULAR LIABILITIES OF THE NATIONAL GOVERNMENT
- AS OF YEAR-END, 2019-2021
- OUTSTANDING EXTERNAL DEBT FROM REGULAR LIABILITIES OF THE NATIONAL GOVERNMENT
- AS OF YEAR-END, 2023-2025
- FOREIGN DEBT SERVICE FOR REGULAR LIABILITIES OF THE NATIONAL GOVERNMENT
- BY CREDITOR, 2022-2024
- OUTSTANDING FOREIGN DEBT FROM REGULAR LIABILITIES OF THE NATIONAL GOVERNMENT
- AS OF YEAR-END, 2017-2019
- PAGSARMINGAN The China-funded Banaoang Pump Irrigation System
- Technical and Institutional Evaluation of Selected National and Communal Irrigation Systems and Characterization of Irrigation Sector Governance Structure
- PROJECT DESCRIPTION FOR SCOPING (UPPER BANAOANG PROJECT) Loan applications and disbursements are still being received and processed as the projects continue to evolve. Ongoing monitoring and evaluation are in place to ensure project continuity.