| Funder | Export-Import Bank of China (China Eximbank) |
|---|---|
| Recipient Organization | Government of Bangladesh |
| Country | Bangladesh |
| Start Date | Jan 21, 2012 |
| End Date | Apr 12, 2028 |
| Duration | 5,926 days |
| Number of Grantees | 1 |
| Roles | Recipient |
| Data Source | AidData Chinese Aid |
| Grant ID | 34230 |
China Eximbank provides RMB 1.6 billion government concessional loan for Shahjalal Fertilizer Factory Project On January 21, 2012, China Eximbank and the Government of Bangladesh signed an RMB 1.6 billion government concessional loan (GCL) agreement and a $325 million preferential buyer’s credit (PBC) agreement for the construction of the Shahjalal fertilizer factory near Fenchugonj Upazila (within the Sylhet District and the Division of Sylhett).
Record ID#34230 captures the GCL, while Record ID#38969 captures the PBC.
According to the Government of Bangladesh’s Economic Relations Division (ERD), the GCL had disbursed RMB 1,269,698,000 as of June 30, 2014 and RMB 1.6 billion as of June 30, 2018 and the PBC had achieved a 100% disbursement rate ($325 million out of $325 million) as of June 30, 2021.
According to the Government of Bangladesh’s ERD, the borrower had made repayments under the GCL worth RMB 106,670,000 as of June 30, 2018, RMB 320,000,000 as of June 30, 2020, and RMB 426,667,000 as of June 30, 2021, and it had made repayments under the PBC worth $86.667 million as of June 30, 2021.
The purpose of this project was to set up a new urea fertilizer factory with a production capacity of 1760 metric tons per day (or 5,80,800 metric tons per year) of granular urea at the premises of Natural Gas Fertilizer Factory Limited (NGFFL) in Fenchugonj Upazila within Sylhet District and the Division of Sylhett.
China National Complete Plant Import and Export Corporation Ltd was the EPC contractor for this project. Its work was overseen by the state-owned Bangladesh Chemical Industries Corporation. China Chengda Engineering Company Ltd. was also involved in project implementation. A foundation stone laying ceremony took place on March 24, 2012.
Construction began on or around the same date. The plant was handed over on February 29, 2016. Its originally expected completion date was June 15, 2015. The factory began commercial production on March 1, 2016.
Government of Bangladesh