| Funder | Export-Import Bank of China (China Eximbank) |
|---|---|
| Recipient Organization | Moroccan National Office of Electricity and Drinking Water (ONEE) |
| Country | Morocco |
| Start Date | Sep 26, 2014 |
| End Date | Jul 31, 2033 |
| Duration | 6,883 days |
| Number of Grantees | 1 |
| Roles | Recipient |
| Data Source | AidData Chinese Aid |
| Grant ID | 30947 |
China Eximbank provides $299.88 million preferential buyer’s credit for 318MW Jerada Coal-Fired Power Plant Construction Project On September 26, 2014, China Eximbank and the Government of Morocco's National Office of Electricity and Drinking Water (French: Office National de l'Electricité et de l'Eau Potable or ONEE) signed a $299.88 million preferential buyer’s credit (PBC) agreement for the 318MW Jerada Coal-Fired Power Plant Construction Project.
The borrower was to use the loan proceeds to finance approximately 85% of the cost of an EPC (commercial) contract, which it signed with Shandong Electric Power Construction Corporation III (SEPCOIII, SEPCO3, or 山东电力建设第三工程公司) on July 25, 2013 (following an international call for tenders).
The specified duration of the EPC contract was 36 months, beginning on December 31, 2014 and ending on December 30, 2017. The purpose of the project was to construct a 318-megawatt coal-fired plant in "Hassi Blal" near the city of Jerada.
The location of the plant is close to the country’s border with Algeria and approximately 60 km south of the city of Oujda (in eastern Morocco).
The plant was to be built on the same site as an existing 165MW Jerada power plant, thereby increasing total on-site power generation capacity to approximately 483 MW. The existing plant was made up of three 55MW units operating on pulverized coal. Coal transport from the port of Nador was provided by train and truck.
The new plant was also designed to operate on pulverized coal and the electricity that it produced was to be evacuated to the Bourdim substation via two new 400 kV transmission lines. Emergency power was to be provided by a new 60 kV transmission line. The two 400 kV lines and the 60 kV line were to be built by ONEE.
A formal groundbreaking ceremony took place on November 19, 2014. However, construction began on October 3, 2014.
The power plant started generating electricity on September 19, 2017 and it was put into commercial operation ahead of schedule on December 18, 2017. Some sources suggest that, upon completion, the power generation capacity of the plant was 350MW rather than 318MW. A post-loan project inspection was undertaken by China Eximbank on June 25, 2019.
Moroccan National Office of Electricity and Drinking Water (ONEE)