Loading…
Loading grant details…
| Funder | China Construction Bank Corporation (CCB)|China Electric Power Equipment and Technology Co. Ltd. (CET)|Industrial and Commercial Bank of China (ICBC) |
|---|---|
| Recipient Organization | Ethiopian Electric Power Corporation (EEPCo) |
| Country | Ethiopia |
| Start Date | Apr 13, 2013 |
| End Date | Oct 19, 2033 |
| Duration | 7,494 days |
| Number of Grantees | 1 |
| Roles | Recipient |
| Data Source | AidData Chinese Aid |
| Grant ID | 30244 |
In 2013, CET, ICBC, and CCB contribute to USD 1.002 billion supplier's credit for 500kV Power Transmission Line of the Great Ethiopian Renaissance Dam (GERD) Project, Ethiopia On April 26, 2013, China Electric Power Equipment and Technology Co, Ltd (CET) — a subsidiary of the State Grid Corporation of China (SGCC) — and the Ethiopian Electric Power Corporation (EEPCO) signed a $1,002,970,414.05 supplier's credit (loan) agreement and commercial contract for the 500kV Power Transmission Line of the Great Ethiopian Renaissance Dam (GERD) Project.
Mihret Debebe from the Ethiopian Electric Power Corporation and Jia Zhi Qiang from SGCC signed the agreement.
The loan's first and last scheduled principal payment dates were June 30, 2016 and December 26, 2027, respectively. Its first and last scheduled interest payment dates were June 30, 2016 and December 26, 2027, respectively.
The borrower was expected to use the proceeds of the loan to finance approximately 85% of a $1.2 billion commercial (EPC) contract between CET and EEPC, which was signed on April 26, 2013. The Ethiopian Government was responsible for directly funding the remaining 15% of the commercial contract cost.
Then, on December 29, 2014, China Construction Bank, the Industrial and Commercial Bank of China (ICBC), and CET signed an accounts receivable financing agreement.
The purpose of the project was to evacuate power from the 6,000 MW Great Ethiopian Renaissance Dam (GERD) via 500kV and 400kV power transmission lines.
The project involved the construction of transmission lines (measuring somewhere between 1,136 km and 1,338 km in length), the construction of two 500kV substations, and the expansion of three existing 400kV substations.
More specifically, the project involved the construction of the 345 km GERD-Dedesa transmission line (two 500kV double circuit transmission lines from GERD to the new Dedesa substation); the construction of the 275 km Dedesa-Holeta transmission line (two 500kV double circuit transmission lines from the Dedesa substation to the Holeta substation); the construction of the Holeta-Akaki II transmission line (a 400kV transmission line from the Holeta substation to the Akaki II substation); the construction of the Holeta-Sebeta II transmission line (a 400kV transmission line from the Holeta substation to the Sebeta II substation); the construction of a Holeta-Sululta II transmission line (a 400kV transmission line from the Holeta substation to the Sululta II substation); the construction of the 500kV Dedesa and Holeta substations; and the expansion of the 400kV Akaki II, Sebeta II, and Sululta II substations.
CET was the EPC contractor responsible for implementation. The project was originally scheduled to begin construction in 2014 and reach completion by 2016. A project kick-off meeting was held in Beijing on January 10, 2014. Then, on March 1, 2014, the project officially commenced. Construction of the first base tower began on August 19, 2014.
The first batch of large equipment -- such as transformers and reactors -- arrived at the Port of Djibouti on December 13, 2014. The wiring construction phase started on January 1, 2015. A project completion certificate was issued on December 22, 2015.
There are indications that the CET loan for the 500kV Power Transmission Line of the Great Ethiopian Renaissance Dam (GERD) Project financially underperformed vis-a-vis the original expectations of the lender. In 2019, the CET loan was restructured to reduce total principal and interest payments by 50% over a 5-year period.
The debt restructuring agreement reportedly provided $18 million of annual cash flow relief to the borrower.
Ethiopian Electric Power Corporation (EEPCo)
Complete our application form to express your interest and we'll guide you through the process.
Apply for This Grant