| Funder | Export-Import Bank of China (China Eximbank) |
|---|---|
| Recipient Organization | Government of Côte d'Ivoire (Ivory Coast) |
| Country | Cote d'Ivoire |
| Start Date | Apr 13, 2012 |
| End Date | Feb 06, 2026 |
| Duration | 5,047 days |
| Number of Grantees | 1 |
| Roles | Recipient |
| Data Source | AidData Chinese Aid |
| Grant ID | 30120 |
China Eximbank provides RMB 602 million government concessional loan for Phase I of Abidjan City Water Supply Project On April 11, 2012, the Chinese Ambassador to Cote d'Ivoire and Ivorian Minister of Foreign Affairs signed a preferential loan framework agreement in which China Eximbank pledged to finance over CFA 100 billion for the Abidjan City Water Supply Project.
Then, on April 13, 2012, China Eximbank and Government of Cote d'Ivoire signed a government concessional loan (GCL) agreement worth RMB 602 million (or CFA 47,031,250,000) for Phase I. The loan was ratified by the Legislature of Cote d'Ivoire on June 27, 2012 (le décret n° 2012-484).
According to the Government of Côte d'Ivoire’s Aid Management Platform (AMP), China Eximbank made 6 loan disbursements (worth CFA 38,498,681,611) between 2012 and 2015: a CFA 3,950,100,000 disbursement on December 31, 2012, a CFA 26,283,100,000 disbursement on December 31, 2013, a CFA 1,970,780,000 disbursement on June 30, 2014, a CFA 3,868,095,000 disbursement on September 30, 2014, a CFA 2,319,450,000 disbursement on January 31, 2015, and a CFA 107,156,611 disbursement on March 15, 2015.
This project involved building infrastructure to distribute water from South Comoé groundwater table in Bonoua to the southern zone of the capital city of Abidjan (in particular, the island of Petit Bassam, which includes the municipalities of Marcory, Koumassi, Treichville and Port-Bouët).
More specifically, it involved an 80,000 m3/day water treatment plant in Bonoua, 2 well fields, 18 wells, 5 ground tanks of 5000 m3 each, a 4000 m3/hour water plant, and 93 km of water pipeline. China Geo-Engineering Corporation (CGC) was the EPC contractor responsible for implementation.
Construction began on March 28, 2013, but the official groundbreaking ceremony did not take place until on August 6, 2013. The project was scheduled to take place over 24 months. It was officially completed and handed over to the Ivorian authorities on March 2, 2015.
One of the main implementation obstacles that this project had to overcome was the displacement of populations in the project area.
The Government of Cote d'Ivoire ultimately agreed to provide CFA 2,990,000,00 (CFA 1,000 per m² of land) of compensations to affected populations.
China Eximbank also provided an RMB 605.5 million (CFA 51.6 million) government concessional loan for Phase II of the project (as captured via Record ID#60789).