Loading…

Loading grant details…

Active Development AidData Chinese Aid

China Eximbank provides RMB 1.045 billion government concessional loan for Robert Gabriel Mugabe International Airport Expansion Project

¥1.05M RMB

Funder Export-Import Bank of China (China Eximbank)
Recipient Organization Government of Zimbabwe
Country Zimbabwe
Start Date Apr 08, 2018
End Date Nov 05, 2032
Duration 5,325 days
Number of Grantees 1
Roles Recipient
Data Source AidData Chinese Aid
Grant ID 26602
Grant Description

China Eximbank provides RMB 1.045 billion government concessional loan for Robert Gabriel Mugabe International Airport Expansion Project On December 6, 2017, the Chinese Government and the Government of Zimbabwe signed a Memorandum of Understanding (MOU) regarding the Robert Gabriel Mugabe International Airport Expansion Project.

Then, on April 8, 2018, China Eximbank and the Government of Zimbabwe signed an RMB 1,045,139,500 ($153 million loan) government concessional loan (GCL) agreement for the Robert Gabriel Mugabe International Airport Expansion Project. The Government of Zimbabwe on-lent the proceeds of the loan to the Civil Aviation Authority of Zimbabwe (CAAZ).

📋 Loan / Grant Terms
📅 Maturity20 years

The borrower is expected to deposit the proceeds from the Air Infrastructure Development Fund and passenger services charges at Harare International Airport into an escrow account with Stanbic (to facilitate the repayment of the loan and as a source of de facto collateral). The escrow account is jointly monitored by the Government of Zimbabwe and China Eximbank.

As of August 2022, the loan had achieved a 85.7% disbursement rate ($131.2 million out of $153 million). Additional disbursements worth $27.8 million took place in 2022, bringing the loan disbursement rate to at least 100%. The loan’s amount outstanding (including principal, interest, and arrears) was $81,231,518.01 as of 2021.

The purpose of the project is to construct a new international terminal building at Robert Gabriel Mugabe International Airport with a construction area of ​​35,000 square meters, a new VIP building, and a satellite command center.

It also involves maintenance on the existing 1.6 km runway, parking lot, and control tower, and the transformation of the existing terminal building and fire center.

The project will also seek to increase the airport’s handling capacity from 2.5 million people per year to six million people per year. China Jiangsu International is the contractor responsible for project implementation. On July 23, 2018, an official project commencement ceremony was held. The project was originally expected to reach completion within 36 months (July 23, 2021).

However, this project has been plagued by scandal, controversy, and delay. In 2019, the Reserve Bank of Zimbabwe diverted $10 million from the project’s escrow account.

China Eximbank then halted disbursements for the project and said that it would not release additional funds until the $10 million withdrawal was returned. It appears that this condition was eventually met because project implementation continued in 2020 and 2021. On February 26, 2020, Chinese Ambassador Guo Shaochun visited Zimbabwe to inspect the airport reconstruction.

As of July 2020, the project achieved a 27% completion rate. China Eximbank also made a $27.7 million loan disbursement in 2020. Then, on September 1, 2021, President Mnangagwa of Zimbabwe visited the project site.

In mid-2022, the Debt Management Office of Zimbabwe’s Ministry of Finance released a report, which provided evidence that the China Eximbank loan for the Robert Gabriel Mugabe International Airport Expansion Project has financially underperformed.

It noted that ‘[t]he low disbursements of loans is due to accumulation of arrears to active China Eximbank loans […] on projects such as the Victoria Falls International Airport ($54 million), NetOne network expansion ($61 million) and expansion of the Robert Gabriel Mugabe International Airport ($3 million).’ It also noted that, by the end of 2021, total external debt arrears to China Eximbank included $13 million for the NetOne Expansion Phase 1 Project, $47 million for the NetOne Expansion Phase 2 Project, $67 million for the Rehabilitation of Municipal Water and Sewage Treatment Works Project (City of Harare Project), $7 million for the National Defence College Project, $54 million for the Victoria Falls Airport Renovation and Expansion Project, $3 million for the Robert G.

Mugabe International Airport Expansion Project, $0.5 million for Phase 2 of the TelOne Broadband Expansion Project, and $73 million for the Medical Equipment and Supplies Project.

As of August 2022, the Robert Gabriel Mugabe International Airport Expansion Project had achieved a 67% completion rate and the Government of Zimbabwe had taken a delivery of 3 (out of 5) radars to support an air traffic control system. Furthermore, sometime in 2022, the rehabilitation of the runways and taxiways were completed.

Near the end of 2022, major outstanding works included refurbishment of the existing building and the procurement of required equipment.

On July 14, 2023, an opening ceremony was held in Harare for the completion and commissioning of the rehabilitated and expanded international terminal building. President Mnangagwa and Chinese Ambassador to Zimbabwe, Zhou Ding, spoke at the ceremony.

Vice President Chiwenga, officials such as the Minister of Finance, the Minister of Transportation, and thousands of locals were also reported to have attended the ceremony.

📋 Staff Comments
  1. This project is also known as the Harare International Airport Expansion Project. The Chinese project title is 穆加贝国际机场改扩建项目.
  2. This airport was formerly known as Harare International Airport.
  3. Loan repayments are supposed to be the first charges made to the escrow account. The remaining balance in the escrow account can be used by the Civil Aviation Authority of Zimbabwe (CAAZ).
  4. Although the rehabilitation and expansion of the international terminal has been completed, as of 2023, the status of remaining project objectives, such as the construction of a new VIP building and fire center, are unknown. Hence, project is believed to still be in implementation.
📚 Sources & References
  • Zim sign $213m deals with China
  • Robert Gabriel Mugabe International Airport Expansion
  • December 2017 China Eximbank Agreement for Robert Mugabe Airport
  • Infrastructure Financing Trends in Africa – 2017
  • 中国向津巴布韦提供项目建设优惠贷款和援助
  • 津巴布韦总统出席中江国际承建的津巴布韦穆加贝国际机场改扩建项目开工仪式
  • NATIONAL ASSEMBLY HANSARD 10 MAY 2018 VOL 44 NO 57
  • A hectic diplomatic 12 months for ED
  • 中企承建津巴布韦最大机场改扩建工程开工
  • 郭少春大使考察穆加贝国际机场改扩建项目
  • Chinese funds continue pouring in
  • 中企承建津巴布韦最大机场改扩建工程开工
  • China Jiangsu International/R.G.M. Airport Project
  • 津巴布韦穆加贝国际机场项目取得新进展
  • US$153m airport expansion on course
  • Zimbabwe's premier airport to undergo Chinese-funded facelift
  • Zimbabwe's premier airport to undergo Chinese-funded facelift
  • 津巴布韦总统出席中江国际承建的津巴布韦穆加贝国际机场改扩建项目开工仪式, http://business.export.by/en/?act=news&mode=view&id=15373
  • Chinese Firms Pour Millions Into Country
  • Zim sign $213m deals with China
  • Zimbabwe goverment sign $213m deals with China to lend Mutirikwi National park as a military base
  • 中企承建津巴布韦最大机场改扩建工程开工
  • 穆加贝国际机场改扩建项目开工仪式在哈拉雷隆重举行
  • 津巴布韦总统参观穆加贝国际机场改扩建工程
  • 驻津巴布韦大使郭少春考察穆加贝国际机场改扩建项目
  • Expansion works on Zimbabwe's RGM Airport well on course
  • DRS Official Commitments from China through 2020
  • ANNUAL PUBLIC DEBT BULLETIN 2020 FINANCIAL YEAR
  • ANNUAL PUBLIC DEBT BULLETIN 2019 FINANCIAL YEAR
  • GOVERNMENT GAZETTE
  • Zimbabwe: Parliament Okays $153m Airport Deal
  • Chinese suspend US$1,3bn projects
  • Zimbabwe chokes under weight of $13 billion China loans
  • Zimbabwe's main airport finally gets radar system from China
  • STATEMENT OF THE PUBLIC DEBT
  • ZWE ANNUAL PUBLIC DEBT BULLETIN 2021
  • ZWE 2021 NATIONAL BUDGET STATEMENT
  • ZWE 2022 MID-TERM BUDGET AND ECONOMIC REVIEW & SUPPLEMENTARY BUDGET
  • Ambassador Zhou Ding of China to Zimbabwe attended the opening ceremony of the new terminal of Mugabe International Airport
  • Zimbabwean president commissions Chinese-funded airport terminal extension
  • Tracking China’s Investment in Overseas Airports
  • The opening ceremony of the new terminal of the Mugabe International Airport expansion project was held, 2023 ZIMBABWE INFRASTRUCTURE INVESTMENT PROGRAMME
  • Cobra Products Chosen for Robert Gabriel Mugabe International Airport Expansion Project
  • Robert Gabriel Mugabe International Airport Expansion
  • Harare
  • Zimbabwe
  • RGM Old Terminal Rehab Complete
  • Zimbabwe THE 2023 NATIONAL BUDGET STATEMENT Loan applications and disbursements are still being received and processed as the projects continue to evolve. Ongoing monitoring and evaluation are in place to ensure project continuity.
All Grantees

Government of Zimbabwe

Advertisement
Apply for grants with GrantFunds
Advertisement
Browse Grants on GrantFunds
Interested in applying for this grant?

Complete our application form to express your interest and we'll guide you through the process.

Apply for This Grant