China funds feasibility studies on the rehabilitation and upgrading of the Musonda hydro power plant in Luapula and Chishimba hydro power plant in Northern Province


Funder Unspecified Chinese Government Institution
Recipient Organization Zambia
Country Zambia
Start Date Dec 29, 2011
End Date Jan 14, 2031
Duration 6,956 days
Number of Grantees 1
Roles Recipient
Data Source AidData Chinese Aid
Grant ID 15518
Grant Description

On December 29, 2011, China and Zambia signed 3 letters of exchange, one of which is to undertake feasibility studies on the rehabilitation and upgrading of the Musonda hydropower plant in Luapula and Chishimba hydropower plant in the Northern Province. It is unclear if the project commenced and how many individuals were involved.

The other two letters of exchange signed are for projects captured in ID#2337 and ID#15507.

📚 Sources & References
  • China Signs Three Contracts with Zambia
  • Zambia: China to Restock Levy Mwanawasa Hospital, http://global.factiva.com/aa/?ref=BBCAP00020111231e7cv001gt&pp=1&fcpil=en&napc=S&sa_from=
  • Zambia
  • China signs economic, technical agreements Loan applications and disbursements are still being received and processed as the projects continue to evolve. Ongoing monitoring and evaluation are in place to ensure project continuity.
All Grantees

Zambia

Advertisement
Apply for grants with GrantFunds
Advertisement
Browse Grants on GrantFunds
Interested in applying for this grant?

Complete our application form to express your interest and we'll guide you through the process.

Apply for This Grant