| Funder | China Ministry of Commerce |
|---|---|
| Recipient Organization | Government of Niger |
| Country | Niger |
| Start Date | Jul 18, 2006 |
| End Date | Feb 02, 2029 |
| Duration | 8,235 days |
| Number of Grantees | 1 |
| Roles | Recipient |
| Data Source | AidData Chinese Aid |
| Grant ID | 135 |
On 18 July, 2006, the Chinese Government agreed to provide an RMB 30 million interest-free loan (captured in linked Record ID#67573) and a RMB 20 million grant (captured in linked Record ID#58623) for the Second Bridge over Niger River Project. However, this was only one of multiple Chinese Government grant and interest-free loan commitments for this project.
In total, China’s Ministry of Commerce reportedly provided RMB 228 million in grants and interest-free loans for this project. This project involved the construction of a 23 meter wide bridge across the Niger River that is 2.15 km in length. China Railway 14th Bureau Co., Ltd. (中国铁建十四局集团) was the contractor responsible for implementation.
A formal foundation-laying ceremony took place on 5 November, 2007; however, construction did not begin until 28 June, 2008.
An official Chinese Government visit to the project site occurred on 14 April, 2010 and progress was deemed to be satisfactory. The bridge ultimately opened for use on 18 March, 2011, and a completion ceremony was held on 8 December, 2012. The contractor originally expected to complete the project by 8 October, 2010.
A 2011 ETCA signed by the Government of Niger and the Chinese Government reportedly also contributed to the funding of the Second Bridge over Niger River Project (captured in linked Record ID#58641).
The Chinese Government also financed and built the third bridge across the Niger River (captured in linked Record ID#58039).