| Funder | Trade and Development Agency |
|---|---|
| Recipient Organization | Delphos International, Ltd. |
| Country | Cote d'Ivoire |
| Start Date | Oct 28, 2024 |
| End Date | Oct 05, 2029 |
| Duration | 1,803 days |
| Number of Grantees | 3 |
| Roles | Recipient |
| Data Source | US Foreign Aid |
| Grant ID | 133517-70 |
This grant funds technical assistance (TA) to support Ecostar Energy, an independent power producer, to assess the financial, technical, socio-environmental, and legal aspects of the development of an estimated 25-megawatt biomass power plant in the Boundiali region of Cote d'Ivoire. Ecostar Energy selected Delphos International (Washington, D.C.) as the sole source contractor to complete the TA.
Delphos International, Ltd.
Complete our application form to express your interest and we'll guide you through the process.
Apply for This Grant