| Funder | Export-Import Bank of China (China Eximbank) |
|---|---|
| Recipient Organization | Government of Botswana |
| Country | Botswana |
| Start Date | Jan 01, 2003 |
| End Date | Jun 22, 2028 |
| Duration | 9,304 days |
| Number of Grantees | 1 |
| Roles | Recipient |
| Data Source | AidData Chinese Aid |
| Grant ID | 119 |
China Eximbank provides RMB 200 million loan for Section 1 of Letlhakeng-Kang Road Project In 2003, China Eximbank and the Government of Botswana signed an RMB 200 million loan agreement for Phase 1 of the Letlhakeng-Kang Road Project (莱特哈肯-康公路(第一阶段)).
Its final maturity date is September 21, 2018. The project involved the construction of a 123 km road segment (“Section 1”) from Letlhakeng to Dutlwe. It was part of a larger 257 km Letlhakeng-Kang Highway Project. Shanxi Construction Engineering Group Corporation was the contractor responsible for implementation.
Construction began in 2003 May and ended in 2005 May.
Section 2 of the Letlhakeng-Kang Highway Project, which ran from Dutlwe to Kang (Morwamosu), was also funded by China Eximbank through two separate loans (as captured via Record ID#109 and Record ID#105).