| Funder | Shanghai Pudong Development Bank Co., Ltd. (SPDB) |
|---|---|
| Recipient Organization | Minera Chinalco Perú S.A. |
| Country | Peru |
| Start Date | Dec 08, 2020 |
| End Date | Feb 19, 2028 |
| Duration | 2,629 days |
| Number of Grantees | 1 |
| Roles | Recipient |
| Data Source | AidData Chinese Aid |
| Grant ID | 108972 |
Shanghai Pudong Development Bank provides RMB 1.314 billion short-term working capital loan for Toromocho Copper Mine On December 8, 2020, Minera Chinalco Perú S.A. (Chinalco Peru or 中铝秘鲁矿业公司) — a special purpose vehicle and wholly owned subsidiary of Aluminum Corporation of China Limited (Chinalco) — entered into a short-term working capital facility agreement with Shanghai Pudong Development Bank worth RMB 1.314 billion.
The Toromocho Project (特罗莫克矿山) is located in central Peru in the core of the Morococha mining district.
It is one of the largest copper mines in the world, and the first greenfield copper mine developed by a Chinese corporation abroad.
This working capital facility supported Chinalco Peru during the Toromocho Expansion (or Phase 2 of the Toromocho Project). The first phase of the expansion works began on June 1, 2018 and was completed during the fourth quarter of 2020.
The second phase of the expansion works was authorized on July 14, 2023, and was initially planned for completion in 2024, but is now expected to be completed in 2025. The combined investment for both phases of the expansion works was $1.355 billion.