| Funder | China Shenhua Energy Company Ltd. |
|---|---|
| Recipient Organization | Erdenes Tavan Tolgoi LLC (ETT) |
| Country | Mongolia |
| Start Date | Oct 18, 2023 |
| End Date | Sep 08, 2032 |
| Duration | 3,248 days |
| Number of Grantees | 1 |
| Roles | Recipient |
| Data Source | AidData Chinese Aid |
| Grant ID | 108484 |
China Shenhua Energy Company Limited provides $300 million PxF facility for Gashuunsukhait-Gantsmod Railway Border (Port) Crossing Project In August 2022, the Chinese Government and the Government of Mongolia a Memorandum of Understanding (MOU) regarding the Gashuunsukhait-Gantsmod Railway Border (Port) Crossing Project.
Then, on May 1, 2023, during a visit to China by Mongolia’s Minister of Foreign Affairs Batmunkhiin Battsetseg, the Chinese Government and the Mongolian Government agreed to intensify the construction work at the Gashuunsukhait-Gantsmod railway border-crossing port.
On October 18, 2023, at the Third Belt and Road Forum in Beijing, China Shenhua Energy Company Limited and Erdenes Tavan Tolgoi LLC (ETT) signed a pre-export finance (PXF) facility agreement worth approximately $300 million for the Gashuunsukhait-Gantsmod Railway Border (Port) Crossing Project. The borrowing terms of the loan (PXF facility) are unknown.
However, it is known that ETT, which is a subsidiary of the Mongolian state-owned company Erdenes MGL, is responsible for repaying the loan with coal export receipts (through a contract between ETT and China Shenhua Energy Company Limited that involves the sale of 20 million tons of coal each year).
The purpose of the project is to construct (a) a 32.7 km railway between Gashuunsukhait and Gantsmod, and (b) a 9.1 km Estakadan bridge that is 31 meters above the ground and capable of transporting 30 million tons of cargo per year.
The project will take place in Khairkhan soum (district) and Khanbogd soum (district) within Ömnögovi (Umnugobi) province.
Upon completion, the Gashuunsukhait-Gantsmod border port is expected to increase economic growth by 1.8-3.2 percent per year, generate an average value of $4.8-$5.4 billion, create about 5,000 new jobs and 1,800-3,200 indirect jobs.
China Railway Design Corporation is the contractor responsible for project design and Tavantolgoi Railway LLC -- a Mongolia state-owned enterprise -- is responsible for project implementation. Construction was originally scheduled to commence in April 30, 2024. However, as of June 2024, there was no evidence that project implementation had commenced.
Erdenes Tavan Tolgoi LLC (ETT)