Africa Growing Together Fund recommits and provides $20 million loan for Urban Water Sector Reform and Akure Water Supply and Sanitation Project in 2021 (Linked to Record ID#36104 and #92006)

$20M USD

Funder People's Bank of China (PBC)
Recipient Organization Government of Nigeria
Country Nigeria
Start Date Sep 01, 2021
End Date Apr 16, 2029
Duration 2,784 days
Number of Grantees 1
Roles Recipient
Data Source AidData Chinese Aid
Grant ID 108052
Grant Description

Africa Growing Together Fund recommits and provides $20 million loan for Urban Water Sector Reform and Akure Water Supply and Sanitation Project in 2021 On May 22, 2014, the African Development Bank (AfDB) and the People's Bank of China (PBOC) signed an agreement for the Africa Growing Together Fund (AGTF) (see Umbrella Record ID#36104).

The purpose of this $2 billion loan facility was to finance large development projects in Africa between 2014 and 2024. The AGTF is sponsored by the PBOC and the administered by AfDB.

Then, on December 12, 2019, AGTF signed an $20 million loan agreement with the Government of Nigeria for the Urban Water Sector Reform and Akure Water Supply and Sanitation Project.

On the same day, the African Development Bank (AfDB) issued a $104.2 million loan and the African Development Fund (ADF) issued an $57 million loan agreement to the Government of Nigeria for the same project.

📋 Loan / Grant Terms
💰 Loan Amountare as follows: a 25-year maturity
📅 Maturity25 years
⏳ Grace Period8 years

The total cost of the project is $222.9 million.

Other project financiers included Ondo State ($36.9 million), the Federal Government of Nigeria ($2.5 million), and the World Bank ($2.3 million).

The Urban Water Sector Reform and Akure Water Supply and Sanitation Project has the following objectives: (i) Provide sustainable access to safe drinking water and sanitation to the residents of Akure City and environs (which cover Ondo City and satellite towns of Idanre, Igbara-Oke, Ilara Mokin, Ibule-Soro and Ipogun); (ii) Establish institutional & organizational arrangements for sustainability of the water and sanitation services; and (iii) Strengthen Federal Government’s capacity to facilitate urban Water Supply and Sanitation (WSS) reform and performance improvements across the country.

The expected project outputs include: (a) a rehabilitated and expanded water supply system, and new sanitation facilities; (b) a fecal sludge treatment plant for Akure City; (c) Ondo Water Corporation, with tariffs, management systems, and pro-poor measures implemented, and meeting full operations and maintenance cost recovery; (d) a hygiene, sanitation and environmental health promotion undertaken, a fecal sludge management system operationalized, and a sanitation and waste water management plan developed with resources mobilized strategy; and (e) a scaled urban water sector program in line with the National WASH action plan.

The main project beneficiaries in Akure and environs are expected to be the 1.3 million residents (48% female) expected to live in the project area (the current population is 0.7 million) who will benefit from improved water services and sanitary conditions. The project was originally expected to be implemented between March 2020 to March 2025.

However, the ADF and AGTF loans were cancelled in April 2020 at the request of Nigeria’s Federal Ministry of Finance, Budget and National Planning to create additional headroom that would allow the African Development Bank to provide COVID-19 Crisis Response Budget Support.

The ADF and AGTF were then reapproved in September 2021, and the project implementation schedule was rescheduled from March 2022 to June 2027.

📋 Staff Comments
  1. The AfDB project identification number is P-NG-E00-014.
  2. The project’s economic rate of return is estimated at 30%, which is is significantly higher than the 12% opportunity cost of capital. An AFDB stakeholder analysis also confirmed that the benefits of the project would mainly accrue to the users of the utility, who are the project’s main economic beneficiaries.
  3. For loan and debt rescheduling records with variable interest rates, AidData calculates the all-in interest rate at T0 based on the reference rate (such as LIBOR or EURIBOR) on the loan start date, plus any known margin. Please see the methodology for additional details.
  4. The margin of 0.8% is calculated by adding the Funding Cost Margin (unknown) to the Lending Margin (0.8%).
📚 Sources & References
  • GPN - Nigeria - Nigerian Urban Water Sector Reform and Akure Water Supply and Sanitation Project
  • Nigeria - Nigeria Urban Water Sector Reform and Akure Water Supply and Sanitation Project
  • Nigeria Urban Water Sector Reform and Akure Water Supply and Sanitation Project
  • ENVIRONMENTAL AND SOCIAL MANAGEMENT PLANFORTHE PROPOSEDURBAN WATER REFORM &AKURE WATER SUPPLY AND SANITATION PROJECTAKURE
  • ONDO STATE
  • NIGERIA
  • Nigeria - Urban Water Sector Reform and Akure Water Supply & Sanitation Project - IPR October 2023
  • Nigeria - Urban Water Sector Reform and Akure Water Supply & Sanitation Project - IPR March 2024
  • Nigeria - Urban Water Sector Reform and Akure Water Supply & Sanitation Project - IPR July 2024
  • Project Appraisal Report
  • October 2019
  • Project Appraisal Report
  • September 2021 Loan applications and disbursements are still being received and processed as the projects continue to evolve. Ongoing monitoring and evaluation are in place to ensure project continuity.
All Grantees

Government of Nigeria

Advertisement
Apply for grants with GrantFunds
Advertisement
Browse Grants on GrantFunds
Interested in applying for this grant?

Complete our application form to express your interest and we'll guide you through the process.

Apply for This Grant