Powerchina Huadong Engineering signs deferred payment agreement (DPA) with Dau Tieng Tay Ninh Energy Joint Stock Company (DTE) for the 240MW Dau Tieng Solar Power Plant


Funder PowerChina Huadong Engineering Corporation Limited
Recipient Organization Dau Tieng Tay Ninh Energy Joint Stock Company (DTE)
Country Viet Nam
Start Date Jun 01, 2018
End Date Mar 29, 2026
Duration 2,858 days
Number of Grantees 1
Roles Recipient
Data Source AidData Chinese Aid
Grant ID 107795
Grant Description

Powerchina Huadong Engineering signs deferred payment agreement (DPA) with Dau Tieng Tay Ninh Energy Joint Stock Company (DTE) for the 240MW Dau Tieng Solar Power Plant In 2018, Dau Tieng Tay Ninh Energy Joint Stock Company (DTE) — a special purpose vehicle and wholly-owned subsidiary of B.

Grimm Power Public Company Limited (B.Grimm), at the time owned by both B.Grimm and Xuan Cau Group — entered into a deferred payment agreement (DPA) with Sinohydro Corporation Limited and Powerchina Huadong Engineering Corporation Limited, both of which are subsidiaries of Powerchina Group. The terms and monetary value of the DPA are unknown.

The purpose of the DPA was to provide short term financing to construct the 240-megawatt (MW) Dau Tieng Solar Power Plant along the western edge of Dau Tieng Reservoir in Tay Ninh Province, Viet Nam. The 240 MW plant was to be part of the wider 420 MW Dau Tieng solar farm. In order to take advantage of a $0.0935 per kilowatt-hour fixed feed-in-tariff offered by the Vietnamese government, B.

Grimm Power Public Company and Xuan Cau Group (the former joint venture co-parent of DTE) created DTE in June 2018 to construct the Dau Tieng solar farm.

This offer required the solar power plants to be completed by June 2019, giving investors little time to seek more sustainable long-term financing. Thus, the power plant was originally financed through equity from B.

Grimm Power Public Company and Xuan Cau Group, as well as the DPA agreement with Sinohydro Corporation Limited and Powerchina Huadong Engineering Corporation Limited.

The project’s local environmental impact assessment report was approved by the People’s Committee of Tay Ninh Province on June 12, 2018 with Decision No. 1483/QDUBND.

The 240MW Dau Tieng Solar Power Plant achieved its commercial operations date (COD) on June 13, 2019 and connected to the national grid. The project was undertaken by Sinohydro Corporation Limited and Powerchina Huadong Engineering Corporation Limited. The solar farm entered into a 20-year Power Purchase Agreement (PPA) with EVN.

It directly serves the electricity demand of Ho Chi Minh City, the commercial center and one of the fastest-growing regions in Viet Nam.

Then, on August 31, 2021, DTE signed a series of loan agreements worth $160.5 million -- including a included a $24,500,000 ‘A loan’ with the Asian Development Bank (ADB); a $128,00,000 syndicated ‘B loan’ agreement with ICBC (Thai), Standard Chartered Bank, Bangkok Bank Public Company Limited (BBL), Kasikornbank Public Company Limited, and Kiatnakin Phatra Bank; and an $8 million loan from Leading Asia’s Private Infrastructure Fund (LEAP) -- in order to restructure the project's financing and provide a longer-term financing solution.

ICBC's contribution to this financing package is captured via Record ID#105189.

In conjunction with the ADB decision to provide financing, the project's environmental and social impacts were reviewed in detail.

The environmental and social measures and the institutional capacity and commitment of DTE to manage the project’s social and environmental impacts according to the requirements of ADB’s Safeguard Policy Statement were deemed adequate. DTE committed to address and implement an environmental and social corrective action plan for the project.

The environmental and social compliance audit report from IBIS proposed a corrective action plan to comply with ADB’s requirements, which included the following: (i) strengthen the environmental and social capacity of the project team, (ii) implement an occupational health and safety plan and emergency plan to respond to operational safety risks and incidents, (iii) implement a waste management plan and strengthen housekeeping practices, and (iv) enhance the project’s grievance redress mechanism and adopt a stakeholder engagement plan.

DTE agreed to implement the corrective action plan to address the gaps before the loan drawdown.

It agreed to regularly report to ADB on the project’s compliance with ADB’s requirements and applicable local environmental, health, and safety laws and regulations.

📋 Staff Comments
  1. The project is also known as the B.Grimm Viet Nam Solar Power Project. The Vietnamese project title is Nhà máy Điện mặt trời Dầu Tiếng. The Chinese project title is 越南油汀光伏项目.
  2. The ADB project identification number is 54013-001.
  3. B.Grimm was established in 1993. It is one of the largest private power generation companies among Thailand’s small power producer operators. As of October 2020, B.Grimm had total generating capacity of 3.0 GW from a diversified portfolio including 17 gas-fired cogeneration plants, 24 solar power plants, and 3 hydropower plants.
  4. DTE was originally established as a joint venture between B. Grimm (55% equity stake) and Xuan Cau Group (45% equity stake). Xuan Cau Group is a large Vietnamese conglomerate.
  5. On May 6, 2020, IBIS Environmental and Social Consulting Asia Pte. Ltd. (IBIS) completed an Environmental and Social Compliance Audit (ESCA) for the project on May 6, 2020.
  6. In a typical deferred payment agreement (DPA), the Chinese company that the project owner in the host country has selected as its engineering, procurement, and construction (EPC) contractor is furthermore a lender to the project owner. The Chinese company assigns receivables under its EPC contract with the project owner to one or more Chinese banks. Upon assignment of receivables, the Chinese bank(s) will release funds to the Chinese company so it can discharge its obligations under the DPA as a lender.
📚 Sources & References
  • Dau Tieng Solar Power Project
  • Dau Tieng Pre issuance assurance statement
  • BGRIM wins green certification for loan
  • Proposed Loan and Administration of Loan Dau Tieng Tay Ninh Energy Joint Stock Company B.Grimm Viet Nam Solar Power Project (Dau Tieng Project) (Viet Nam)
  • Viet Nam : B.Grimm Viet Nam Solar Power Project (Dau Tieng Project)
  • Viet Nam: B.Grimm Viet Nam Solar Power Project – (Dau Tieng Project)
  • Tip-apa Limvichai
  • V. Joseph Tisuthiwongse
  • Bringing life to South East Asia’s largest solar farm project in Vietnam
  • ADB approves funds to refinance solar power project in Vietnam
  • VILAF advised B.Grimm Power in the US$160.5 green loan financing of Dau Tieng Solar Farm
  • ADB approves refinancing of Vietnam solar farm
  • Dau Tieng Solar PV Plant Phase 2 (240MW) Refinancing 2021
  • 研究报告, “一带一路”国家 可再生能源项目 投融资模式、问题和建议
  • 东南亚最大光伏项目竣工投产 中国电建承建 Loan applications and disbursements are still being received and processed as the projects continue to evolve. Ongoing monitoring and evaluation are in place to ensure project continuity.
All Grantees

Dau Tieng Tay Ninh Energy Joint Stock Company (DTE)

Advertisement
Discover thousands of grant opportunities
Advertisement
Browse Grants on GrantFunds
Interested in applying for this grant?

Complete our application form to express your interest and we'll guide you through the process.

Apply for This Grant