| Funder | China Development Bank (CDB) |
|---|---|
| Recipient Organization | DET-AL Aluminium LLC |
| Country | Azerbaijan |
| Start Date | Jan 01, 2013 |
| End Date | May 21, 2030 |
| Duration | 6,349 days |
| Number of Grantees | 1 |
| Roles | Recipient |
| Data Source | AidData Chinese Aid |
| Grant ID | 105648 |
In 2013, China Construction Bank and China Development Bank contribute to USD 30 million syndicated buyer’s credit for Phase 2 of DET-AL Ganja Aluminum Plant Construction Project, Azerbaijan In 2013, DET-AL Aluminium LLC (DET.AL Aluminium LLC) — a special purpose vehicle and wholly-owned subsidiary of Det.AL Holding — signed a $30 million syndicated buyer’s credit facility agreement with China Development Bank (CDB) and China Construction Bank (CCB) for Phase 2 of the DET-AL Ganja Aluminum Plant Construction Project.
However, it is known that the borrower was expected to use the loan proceeds to partially finance a commercial (EPC) contract with Sichuan Machinery & Equipment Import & Export Co. Ltd. (四川省机械进出口有限公司).
The purpose of Phase 2 is to increase the capacity of an aluminium smelter complex in Azerbaijan’s Ganja district from 60,000 tons per year to 160,000 tons per year. Sichuan Machinery & Equipment Import & Export Co. Ltd. (四川省机械进出口有限公司) was the EPC contractor responsible for implementation.
Phase 2 trial operations commenced in September 2013 and Phase 2 was originally scheduled to reach completion by mid-2015.
DET-AL Aluminium LLC
Complete our application form to express your interest and we'll guide you through the process.
Apply for This Grant